60

Sandpiper Playground at Rockaway Beach is currently under active construction. June 2019 is the projected completion date. The playground will include a water area, two play area and two swing sections. Total funding for this playground is $5,860,000.

Design Start Date: January 2015
Projected Completion Date: May 2016
Completion Date: June 2017

Procurement Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: n/a

Sandpiper Playground Reconstruction Current Condition Rockaway Beach Queens NYC therockawaysny